Aldesa It was awarded two 400 kV electricity transmission contracts in Polonia for a value exceeding 50 million euros. The projects were commissioned by the operator. Polskie Sieci Elektroenergetyczne (PSE), will modernize the northern grid to integrate offshore wind energy.
The global company Aldesa[Company Name], a leader in the construction, energy and concessions sectors, has taken a strategic step in its consolidation within the energy market of Europa Central. The award, managed through the Polish electricity system operator PSEIt includes the development of critical 400 kV infrastructure that will allow the transport of clean energy from future wind farms in mar Báltico towards the rest of the country.
Award details and contract breakdown
The first contract, valued at approximately 37 million euros, focuses on the section between the towns of Choczewo, Gdańsk Błonia y Grudziądz WęgrowoThis intervention is key to the capillarity of the electrical system in regions with high demand for technical stability.
The second contract, meanwhile, has a budget of approximately €16 million. This project is designed to carry out the technical connection of the substation of Choczewo with the line now operational Słupsk–Żarnowiec, optimizing cargo flow in the coastal area of influence.
| Transmission Project (400 kV) | Location / Section | Approximate Budget |
|---|---|---|
| Main Section Contract | Choczewo Gdańsk Błonia Grudziądz Węgrowo | 37.000.000 € |
| Substation Connection | Substation Choczewo - Line Słupsk–Żarnowiec | 16.000.000 € |
| Total Joint Investment | North of Polonia | > 50.000.000 € |
Impact on the energy transition and the firm's trajectory
Both actions are integrated into the national strategic infrastructure de PoloniaThe main objective is to ensure that the electricity grid is able to efficiently absorb and distribute the massive renewable energy generation expected from [the projected period]. mar Bálticothus reinforcing the country's energy security and decarbonization goals.
Aldesa It is not a new player on this scene. The firm has a strong track record of specialization in infrastructure. very high voltageSpecifically in Polish territory, the company has already completed the construction of approximately 280 kilometers of lines, establishing itself as a preferred partner for industrial energy development.
With over 50 years of experience and an active presence in 15 countries, Aldesa It employs more than 2.500 professionals. Its business model is based on offering comprehensive solutions in building, industry, and technology, always under criteria of profitability and operational sustainability.
Key points and frequently asked questions about Aldesa's projects in Poland
What is the main objective of these new 400 kV lines?
The fundamental purpose is to strengthen the electrical grid in the north of Polonia to enable the integration and transport of renewable energy generated by the new offshore wind farms of mar Báltico.
Who is Aldesa's main client in these contracts?
The client is Polskie Sieci Elektroenergetyczne (PSE), which acts as the national operator of the electricity system in Polonia.
What experience does Aldesa have in the Polish energy market?
Aldesa has built approximately 280 kilometers of power lines in Polonia, participating in projects essential to the stability of the country's energy system.