GES completes a 200 MW wind farm for EDPR in Mexico

Executed under the highest safety and quality standards

Global Energy Services has completed the construction and installation of a project in the Coahuila area.


[Img # 22396]Global Energy Services (GES) has just completed the construction of a 200 MW wind farm in Mexico. The project is among the five largest projects carried out by GES so far in the country and includes the complete construction of the park: civil works, medium voltage network, the lifting substation, high voltage evacuation line and interconnection substation.

 

GHG It has also been in charge of installing the 95 wind turbines that make up the park. All of this executed under the highest safety and quality standards.

 

EDPR has relied on the experience of GES in Mexico for the execution of its first project in the country. The magnitude of the project has required a significant logistical and human effort. The civil works have included the foundations of the 95 wind turbines, as well as 60 kilometers of roads and three bridges.

 

 

The project is among the five largest projects executed by GES so far in the country

 

 

Regarding the electrical work, the medium voltage network adds 100 km of cable, to which another 20 kilometers of the high voltage line must be added.

 

GES' experience in Mexico is supported by its more than 10 years in a market in which it has built 733 MW, to which we must add 1 GW in installation. Mexico It is a strategic market for GES, with enormous potential for the company's wind and photovoltaic activity.