HOCHTIEF has formalized a strategic contract with Trafikverket for the design and expansion of a 26-kilometer section of the railway line East Link, in the vicinity of Estocolmo, Suecia, with an estimated investment of 900 million euros.
Rail expansion in the Scandinavian market
The project, called OL31 VagnhäradIt is located southwest of the Swedish capital and represents a fundamental link in the planned 160-kilometer future rail connection between Järna y LinköpingThe contract is being awarded under a collaborative model with the Swedish transport authority, guaranteeing high-precision technical integration into an infrastructure that will be key to sustainable mobility in the north of Sweden. Europa.
Juan Santamaría, CEO of the Grupo ACS and HOCHTIEF, highlighted the importance of this operation: “Our comprehensive capabilities as a leading provider of infrastructure and services allow us to offer high-quality rail assets. With the expansion of this rail link in Suecia"We are making a significant contribution to the growth of an efficient and sustainable transport infrastructure."
Technical details and implementation schedule
The technical complexity of the section OL31 Vagnhärad This includes the design and construction of several tunnels, large bridge structures, and a new train station. According to the schedule set by the entities involved, the construction phase will continue uninterrupted until 2034.
| Concept | Project Details |
|---|---|
| Estimated Budget | 900 million EUR (9.500 billion Swedish kronor) |
| Length of the Section | 26 kilometers |
| Expected Completion | Year 2034 |
| Main client | Trafikverket (Swedish transport administrator) |
Global leadership in transport infrastructure
This award strengthens the order book of HOCHTIEF in the high-speed rail segment internationally. Currently, the company manages large-scale projects in several strategic markets:
- Estados UnidosConstruction of a main section of the high-speed train California.
- AustraliaProject development Logan and Gold Coast Faster Rail.
- Alemania: Expansion of 42 kilometers of double track on the right bank of the Rin all with Deutsche Bahn.
Key points and frequently asked questions about the railway project in Sweden
What is the scope of HOCHTIEF's contract in Sweden?
The contract includes the design and expansion of 26 kilometers of the line East Link (project OL31 Vagnhärad), including tunnels, bridges and a railway station.
What is the economic value and timeframe of the project?
The investment is estimated at 900 million euros (approximately 9.500 billion Swedish kronor) and the works are expected to be completed in 2034.
Who is the client and under what working arrangement do we operate?
The client is Trafikverket, the transport authority of Suecia, and the project is being developed under a technical and construction collaboration agreement.