| Date | Operation Summary | Key Figures / Investment | Destination Country |
|---|---|---|---|
| 2023-06-05 |
Abengoa participated in the official opening and was the EPC contractor for the Jubail 3A desalination plant in Saudi Arabia, the world's largest partially solar-powered plant, with a capacity of 600.000 m3/day.
|
Capacity of 600.000 m3/day; Satisfies the demand of 3.000.000 inhabitants | Saudi Arabia |
| 2023-04-21 |
Abengoa, in consortium with SEPCOIII, has begun commercial operation of phase two of the Taweelah desalination plant in Abu Dhabi. It is the world's largest reverse osmosis plant, guaranteeing the water supply and combining its production with clean energy.
|
Total production of 909.218 m3/day; phase one desalinated 450.000 m3/day; photovoltaic solar field of more than 70 MWp; supplies 4,5 million people. | United Arab Emirates |
| 2023-04-13 |
Abengoa has completed and transferred the Jubail 3A desalination plant in Saudi Arabia, strengthening its global leadership in desalination. The plant, which produces 600.000 m³/day of potable water, is the world's largest partially solar photovoltaic plant.
|
Production of 600.000 m³/day of drinking water for 3.000.000 inhabitants. 45,5 MWp photovoltaic solar plant. | Saudi Arabia |
| 2015-12-17 |
Abengoa was awarded a contract worth more than USD 200 million for the engineering and construction of the largest combined cycle power plant in Jamaica, a 190 MW plant that will replace a fuel-oil plant.
|
Contract worth over USD 200 million, 190 MW plant, creation of between 300 and 500 jobs. | Jamaica |
| 2015-09-14 |
Abengoa has been selected by Transco to build a 23 km, 400/220 kV power transmission line in Abu Dhabi, United Arab Emirates. This project reinforces its presence and leadership in the sector in the Middle East.
|
22 M€ | United Arab Emirates |
| 2015-09-10 |
Abengoa has been awarded a €38 million contract to carry out the electromechanical installations for the new Nyt Hospital complex in Herlev, Denmark. The project will last 24 months.
|
38 millones de euros | Denmark |
| 2015-09-04 |
Abengoa has signed a framework agreement with the National Autonomous University of Mexico (UNAM) to promote the professional development of students and the training of its employees, consolidating its relationships with educational institutions in the country.
|
Mexico | |
| 2015-09-01 |
Abengoa has been awarded a contract for the construction of new sanitation works in Ciudad de la Costa, Uruguay, for the state-owned company OSE, reaffirming its leadership in the country.
|
Investment exceeding 13 million dollars | Uruguay |
| 2015-08-27 |
Abengoa, through its Uruguayan brand Teyma, has won a public tender in Uruguay for the construction of the Capurro fishing port in Montevideo. The project, valued at 81 million euros, aims to free up space in the main port and promote the maritime industry and tourism.
|
81 millones de euros | Uruguay |
| 2015-08-11 |
Abengoa has been selected to build the world's largest biomass-fired power and steam plant in Teesside Port, UK, with a capacity of 299 MW.
|
Contract worth more than €600 million and creation of up to 1.100 jobs. | United Kingdom |
| 2015-07-24 |
Abengoa has closed the financing of Uruguay's first public-private partnership project, which consists of the construction, maintenance and operation of a 50.000 m2 penitentiary center in Montevideo.
|
90 MUSD | Uruguay |
| 2015-07-20 |
Abengoa, together with its Israeli partner Shikun & Binui, has closed the financing for the construction of Ashalim, Israel's largest solar thermal power plant, marking a milestone in its internationalization.
|
Total investment of US$1.000 billion. It will create 633 jobs during construction and 60 in operation. | Israel |
| 2015-07-14 |
Abengoa, in consortium with Starwood Energy, has been awarded a contract to finance, build, operate and maintain a 500 kV electric transmission line in California and Arizona, United States, consolidating its position in the market.
|
Total investment of approximately $300 million | United States |
| 2015-06-02 |
Abengoa has been selected by Mexico's CFE to develop four new substations in Sinaloa. The company will be responsible for the engineering, design, construction, and commissioning, consolidating its leadership in electricity transmission in the Mexican market.
|
Total investment of $8,7 million for the four substations. Implementation period of 16 months. | Mexico |
| 2015-05-28 |
Abengoa has begun construction of the Tres Mesas wind farm in Tamaulipas, Mexico. The project, with 45 wind turbines and a capacity of 148,5 MW, consolidates its leadership in the renewable energy sector in the country.
|
45 wind turbines, 148,5 MW capacity, energy for 71.000 homes | Mexico |
| 2015-05-27 |
Abengoa has received environmental approval for Atacama 2, its second 210 MW solar complex in Chile. This project, which includes a concentrated solar power (CSP) plant and a photovoltaic (PV) plant with storage, will create 2.000 jobs and strengthens its presence in the country.
|
A 210 MW solar complex (110 MW concentrated solar power and 100 MW photovoltaic). It will generate 2.000 jobs. | Chile |
| 2015-05-13 |
Abengoa and Enel have been selected by Pemex to develop a 517 MW cogeneration plant in Oaxaca, Mexico. The project, with an investment of US$950 million, will supply electricity and steam to Pemex and sell the surplus.
|
Investment of 950 million USD, 517 MW plant | Mexico |
| 2015-05-05 |
Abengoa has been selected to build the first biorefinery in the US that will produce aviation biofuels from municipal solid waste, consolidating its presence in the country.
|
$200 million contract; will generate more than 500 jobs in construction and 100 in operation; will produce more than 10 million gallons of biofuels per year. | United States |
| 2015-05-04 |
Abengoa has been awarded two new water treatment projects in Colombia, one for wastewater in Madrid-Cundinamarca and another for drinking water supply in Yopal-Casanare, consolidating its presence in the Colombian market.
|
Total investment of €29 million | Colombia |
| 2015-05-04 |
Abengoa has signed a memorandum of understanding with the Government of Egypt to collaborate on the development of solar thermal and photovoltaic plants, laying the foundations for a technical and commercial relationship in the renewable energy sector.
|
Installed capacity of 1.603 MW in commercial operation, 360 MW under construction and 320 MW under development, distributed across 32 plants worldwide. | Egypt |
| 2015-04-20 |
Abengoa has inaugurated the first desalination plant in West Africa, in Accra, Ghana. The plant will produce 60.000 m³ of drinking water per day, supplying 500.000 residents under a 25-year BOOT (Build-Operate-Operate-Transfer) model.
|
60.000 m3 of drinking water per day, 500.000 residents, 400 jobs, US$1.300 billion in revenue over 25 years. | Ghana |
| 2015-04-01 |
Abengoa has been recognized for the third consecutive time as a member of the Ethibel Sustainability Index (ESI) Excellence Europe, consolidating its global leadership in environmental management, corporate social responsibility and good governance.
|
||
| 2015-03-27 |
Abengoa and EIG Global Energy Partners have signed an agreement to create Abengoa Projects Warehouse-1 (APW-1), an investment vehicle that will finance the construction of renewable and conventional energy projects, and energy transmission in Mexico, Brazil and Chile.
|
Total capital initially committed is $2.000 billion, with $1.100 billion invested by EIG and the remaining 45% by Abengoa. Abengoa expects to receive an initial payment of $500 million. | Chile, Mexico, Brazil |
| 2015-03-13 |
Abengoa has secured $660 million in financing for the construction of Xina Solar One, a 100 MW concentrated solar power plant in South Africa, in partnership with local companies, which will supply clean energy to Eskom.
|
Financing of $660 million, total investment of $880 million, 100 MW plant, creation of more than 1.300 jobs in construction and 45 in operation. | South Africa |
| 2015-03-13 |
Abengoa has been awarded a contract to build approximately 400 km of electric transmission lines in Newfoundland and Labrador and Nova Scotia, Canada, as part of a project to transport renewable energy.
|
Project valued at 155 million USD, construction of 400 km of transmission lines, creation of 200 jobs. | to Canada |
| 2015-03-11 |
Abengoa has established a strategic collaboration with the Honors College of the University of Houston (United States) to develop programs in renewable energy and technological advances, including its Waste to Biofuels technology.
|
United States | |
| 2015-03-09 |
Abengoa has started construction of a desalination plant in Agadir, Morocco, with the capacity to supply more than 500.000 people, ensuring the water supply and supporting the tourism and agricultural development of the region.
|
Financing of €82M; capacity of 100.000 m3/d of drinking water for 500.000 people. | Morocco |
| 2015-03-02 |
Abengoa, in public-private collaboration with IDC and KaXu Community Trust, has inaugurated KaXu Solar One, South Africa's first commercial solar thermal power plant, with the capacity to supply 80.000 homes.
|
Investment of $891 million, generation of $516 million in taxes and creation of more than 1.000 jobs. | South Africa |
| 2015-02-03 |
Abengoa and EIG Global Energy Partners are finalizing the creation of Abengoa Projects Warehouse 1 (APW1), a joint venture that will invest in a portfolio of energy and water projects in the US, Mexico, Brazil and Chile.
|
Initial investment of $2.500 billion; total investment managed by APW1 of more than $9.200 billion. | USA, Mexico, Brazil, Chile |
| 2015-01-28 |
Abengoa has signed a research agreement with the Masdar Institute and Masdar in Abu Dhabi to optimize membrane distillation technology in brine treatment, improving the performance of desalination plants and environmental sustainability.
|
The pilot plant will produce 1.000 m³/day of desalinated water. Abengoa has the capacity to treat five million m³ of water per day worldwide, of which 1,5 million is desalinated water. | United Arab Emirates |
| 2015-01-27 |
Abengoa has celebrated the start of construction of the photovoltaic plant that will be part of the Atacama 1 solar complex in Chile, the largest in Latin America, with a total capacity of 210 MW.
|
The Atacama 1 complex, with a capacity of 210 MW (100 MW photovoltaic, 110 MW concentrated solar power), will prevent the emission of 870.000 tons of CO2 per year. | Chile |
| 2015-01-21 |
Abengoa, in collaboration with Advanced Water Technology (AWT), will develop the world's first large-scale desalination plant powered by solar energy in Saudi Arabia, a project valued at USD 130 million to supply the Al Khafji region.
|
Project valued at 130 million USD. Capacity of 60.000 m3 of desalinated water per day. | Saudi Arabia |
| 2015-01-13 |
Abengoa has been awarded a contract with the Federal Electricity Commission (CFE) in Mexico for the construction and operation of the 38 CC Norte III Combined Cycle Thermoelectric Power Plant, with a capacity of 906 MW.
|
Capacity of 906 MW, price of 0.7446 pesos per kilowatt-hour, contract for 25 years, savings of 1,740 million pesos for CFE. | Mexico |
| 2015-01-07 |
Abengoa and EIG Global Energy Partners have signed an agreement to create a new company (NewCo) that will jointly invest in the development of Abengoa's construction projects in the energy and environment sectors worldwide.
|
Investment in the asset portfolio exceeds $9.500 billion. | USA, Mexico, Brazil, Chile |
| 2014-12-23 |
Abengoa and South Korea's Daelim signed a memorandum of understanding in Seoul to jointly develop major hydraulic infrastructure projects worldwide, combining their strengths in different products and markets.
|
Global | |
| 2014-12-22 |
Abengoa has been selected to develop five new electricity transmission projects in Chile, including an 87 km line and the expansion of four substations, consolidating its position in the country.
|
Investment of 40 million USD, 380 jobs created, 87 km line. | Chile |
| 2014-12-19 |
Abengoa has been awarded a contract to supply 950 GWh/year of energy in Chile for 15 years, generated through a combination of solar thermal and photovoltaic plants, within the framework of a competition by the Chilean Ministry of Energy.
|
Supply of 950 GWh/year for 15 years. Solar plants with 110 MW of concentrated solar power and 100 MW of photovoltaic power. | Chile |
| 2014-12-19 |
Abengoa has been awarded the third prize for excellence by the African Development Bank for its Ain Beni Mathar hybrid solar-gas power plant in Morocco, recognizing its contribution to sustainable development and its expertise in energy and the environment in Africa.
|
A 472 MW plant that generates 10% of Morocco's energy. It develops desalination plants with a capacity of over 660.000 m³ of water/day, more than 1.600 km of power lines, and solar plants that generate over 870 MW. | Morocco, South Africa, Algeria |
| 2014-12-17 |
Abengoa has been selected to develop a new $27,2 million electricity transmission project in central Argentina to supply power to a new steel plant.
|
$ 27,2 million | Argentina |
| 2014-12-16 |
Abengoa has inaugurated its second wind farm in Uruguay, Talas del Maciel II, Cadonal, consolidating its position as the main generator of wind energy in the country with a 20-year concession.
|
Investment of US$127 million. The park will generate 50 MW. Both of Abengoa's wind farms in Uruguay will generate 100 MW. | Uruguay |
| 2014-12-15 |
Abengoa has signed a power purchase agreement and secured financing for Xina Solar One, a 100 MW concentrated solar power plant in South Africa, with an investment of one billion dollars.
|
$1.000 billion investment. 100 MW plant. Creation of more than 1.300 jobs during construction and 45 during operation. Abengoa controls 40% of the consortium. | South Africa |
| 2014-12-15 |
Abengoa has secured long-term financing for the construction, operation and maintenance of the El Zapotillo Aqueduct in Mexico, a project that consolidates its experience in hydraulic infrastructure in the country.
|
Total project investment: $640 million. | Mexico |
| 2014-12-09 |
Abengoa and Hyundai E&C have signed a memorandum of understanding in Seoul to jointly develop power plants. This strategic alliance aims to leverage synergies and gain a competitive advantage in future concentrated solar power (CSP) and hybrid power plant projects worldwide.
|
South Korea | |
| 2014-12-09 |
Abengoa, in consortium with Sarooj, has been awarded a €20M contract in Oman to build an electrical substation and a transmission line, reinforcing its presence in the country's energy sector.
|
€20 million investment, 40 direct jobs and 150 indirect jobs | Oman |
| 2014-12-05 |
Abengoa has closed the long-term financing of 90,1 million USD for its second 50 MW wind farm in Uruguay, allowing the early repayment of a bridge loan and bringing forward the start of operations.
|
Financing of 90,1 million USD; early repayment of 60 million USD in bridge loan; 50 MW wind farm. | Uruguay |
| 2014-11-27 |
Abengoa, as Manchester United's Official Sustainable Technology Partner, has launched the "Reds Go Green" competition. This initiative aims to promote awareness of renewable energy and sustainability among the club's supporters, offering match tickets as prizes.
|
United Kingdom | |
| 2014-11-24 |
Abengoa has been awarded a €23M contract for the engineering, construction, maintenance and operation of a 210km electricity transmission project in Morocco, improving the interconnection with Algeria.
|
23 M€ | Morocco, Algeria |
| 2014-11-07 |
Abengoa will develop a 20 MW hydroelectric plant in Peru for Hidroeléctrica Laguna Azul, a project valued at more than 50 MUSD that will supply clean energy to more than 10.000 homes and prevent the emission of 43.000 tons of CO2 per year.
|
Investment of more than 50 million USD; Installed capacity of 20 MW; Will supply 10.000 homes; Will prevent 43.000 tons of CO2 per year; Will generate more than 200 direct and 600 indirect jobs. | Peru |
| 2014-11-05 |
Abengoa has been selected by Belgian Eco Energy to develop the world's largest biomass plant in Ghent, Belgium, which will produce 215 MW of electricity and 100 MW of thermal energy.
|
The project cost will exceed €315 million. The plant will produce 215 MW of electricity and 100 MW of thermal energy. It will create up to 1.100 jobs. | Belgium |
| 2014-11-04 |
Abengoa has acquired BrightSource Energy's stake in the Palen Solar Energy Generating Station project in California, becoming the sole developer. It will utilize its molten salt tower technology with storage to meet the energy needs of the Californian market.
|
United States | |
| 2014-11-03 |
Abengoa, leading the Vista Ridge Consortium, is awarded a 30-year contract for the design, construction, financing, operation and maintenance of the water supply for San Antonio, Texas, United States.
|
30-year contract to transport 168.970 m3/day of water through a 225 km aqueduct. | United States |
| 2014-10-28 |
Abengoa has been recognized for the third consecutive year as a leader in transparency and performance in climate change management in the CDP Iberia 125 report, highlighting its commitment to sustainable development.
|
Rating of 99 out of 100 in transparency and A in performance. | Spain, Portugal |
| 2014-10-23 |
Abengoa has been recognized by the CDP Climate Performance Leadership Index 2014 as one of the 200 global companies with excellent performance in climate change, being the only Spanish company in the industrial sector.
|
Recognized among 200 global companies; 40 in the industrial sector; backed by 767 investment institutions representing 92 trillion dollars. | Global |
| 2014-10-20 |
Abengoa has opened its first commercial-scale second-generation cellulosic ethanol plant in Hugoton, Kansas, USA, transforming crop waste into sustainable biofuel.
|
Production capacity of up to 25 million gallons per year; generates 21 megawatts (MW) of electricity. | United States |
| 2014-09-29 |
Abengoa, a Spanish sustainable technology company, is partnering with Manchester United (UK) to improve the club's sustainable business practices by identifying and implementing solutions to save resources and reduce waste.
|
United Kingdom | |
| 2014-09-29 |
Abengoa has been awarded a new electricity transmission project in Argentina, valued at US$147 million. It will be responsible for the design, engineering, construction, and commissioning of 176 km of lines and transformer substations, creating 250 jobs.
|
147 million USD, 176 km of transmission lines, 33 months of execution, 250 jobs | Argentina |
| 2014-09-24 |
Abengoa, in consortium with Siemens, has been awarded a project for the supply, construction and commissioning of a 230 kV electrical transmission substation in Costa Rica, connecting the Reventazón hydroelectric project.
|
$ 15,7 million | Costa Rica |
| 2014-09-19 |
Abengoa has been selected by Kuwait's Ministry of Electricity and Water to develop a new power transmission project, which includes the design, supply and construction of three high-voltage power lines.
|
€20,5M value, 86 km of lines, 20 months of execution. | Kuwait |
| 2014-08-14 |
Abengoa reported that 39% of its revenue for the first half of 2014 came from North America (USA and Mexico), solidifying this region as its main source of income. Geographic diversification is key to its strategy.
|
Sales of €3.405 million, EBITDA of €695 million, net profit of €69 million, and 39% of revenue comes from the USA and Mexico. | USA, Mexico, Spain |
| 2014-06-20 |
Abengoa, leading the Vista Ridge consortium, has been shortlisted by the San Antonio Water System to develop a drinking water supply project in Texas, USA, guaranteeing a fixed price for 30 years.
|
Generation of almost 62 Mm3 annually, pipeline of 225 km, project duration of 30 years. | U.S. |
| 2014-06-11 |
Abengoa, together with NREL and the Colorado School of Mines, has been selected by the U.S. Department of Energy to develop a new solar thermal storage technology, leading the systems integration and techno-economic analysis.
|
Investment of €1,3 million by the U.S. Department of Energy. | U.S. |
| 2014-06-02 |
Abengoa has been awarded a contract in Morocco to develop a desalination plant in Agadir. The plant, with an investment of €82 million, will produce 100.000 m³ of drinking water daily, supplying 800.000 people.
|
Investment of €82 million, production of 100.000 m3 of drinking water daily, supply to 800.000 people, operation and maintenance for 20 years. | Morocco |
| 2014-05-06 |
Abengoa has been selected by Masdar to develop a pilot desalination plant with innovative reverse osmosis technology in Abu Dhabi, United Arab Emirates, consolidating its commitment to R&D and sustainable solutions.
|
Project budget: US$7,9 million | United Arab Emirates |
| 2013-08-26 |
Abengoa has been selected by Ukrenergo to develop an electric power transmission project in Ukraine, building a 187 km line from the Zaporizhia nuclear power plant to the Kakhovska substation.
|
55 M€ | Ukraine |